PLN Utilities in Mampang-Kuningnan Underpass Construction will Be Relocated
Reported by Wuri Setyaningsih | Translated by Maria Inggita
Jakarta Bina Marga Dept. has coordinated with National Electricity Company (PLN) related to utilities inside Mampang-Kuningan underpass construction area, Setiabudi, South Jakarta.
We targeted construction to finish in the end of this year
"We already coordinated with PLN side to relocate the cables," said Yusmada Faizal, Head of Jakarta Bina Marga Dept. when observing Mampang-Kuningan underpass construction location, Monday (7/24).
According to him, cable relocation work can affect construction time target. At first, construction was targeted to be done at the end of 2017. But if cable relocation is not done immediately, then it will make the construction time to be overdue.
Flyover Construction is Slated in September"We targeted construction to finish in the end of this year. But if cable problem is still not fully resolved, maybe the construction time will be delayed," he added.
Currently, he continued, underpass construction has reached 36 percent.